In NIMS, when do managers plan and prepare for the demobilization process? A. At the end of the incident. B. During recovery. C. At the same time they begin mobilizing resources. D. When transitioning between operational periods.
In NIMS, managers plan and prepare for the demobilization process At the same time they begin mobilizing resources.