Solution:
If 3 men can complete the task in 3 days, it means that the rate of work is 3 man-days per day (3 men * 3 days = 9 man-days of work in total).
Now, if 6 men are working together, their combined rate of work will be 6 times that of one man working alone.
So, it will take 9 man-days / 6 men = 1.5 days for 6 men to dig the trench.
Added 9/19/2023 11:48:40 AM
This answer has been confirmed as correct and helpful.
3
Solution:
5 men * 12 days = 60 man-days to complete the job.
6 men * x days = 60 man-days
x = 60 man-days / 6 men
x = 10 days
So, it will take 6 men 10 days to complete the same job at the same rate.