-Why is it necessary to track actual and committed costs once a project starts?
Once the project starts it is necessary to keep track of the actual cost and the committed cost as they can be compared with the CBC. [ To keep track of he actual cost it is necessary to maintain an information system to collect data on a regular and timely basis. Such a type of system should include all the details of money spend over a period of time. Committed costs are also known as
commitments or encumbered costs. Costs are committed when a resource needed for the project is ordered. ]
Expert answered|rhyann24|Points 1965|
Question
Asked 10/16/2011 10:58:59 AM
0 Answers/Comments
Get an answer
New answers
Rating

There are no new answers.

Comments

There are no comments.

Add an answer or comment
Log in or sign up first.
23,892,754 questions answered
Popular Conversations
Weegy Stuff
S
Points 301 [Total 698] Ratings 0 Comments 301 Invitations 0 Offline
S
P
P
Points 181 [Total 988] Ratings 0 Comments 181 Invitations 0 Offline
S
1
L
L
P
R
P
L
P
Points 120 [Total 11293] Ratings 0 Comments 120 Invitations 0 Offline
S
L
P
Points 46 [Total 2114] Ratings 0 Comments 46 Invitations 0 Offline
S
Points 17 [Total 301] Ratings 0 Comments 17 Invitations 0 Offline
S
R
Points 11 [Total 447] Ratings 0 Comments 11 Invitations 0 Offline
S
Points 4 [Total 904] Ratings 0 Comments 4 Invitations 0 Offline
S
Points 2 [Total 2] Ratings 0 Comments 2 Invitations 0 Offline
S
Points 1 [Total 2] Ratings 0 Comments 1 Invitations 0 Offline
S
Points 1 [Total 2] Ratings 0 Comments 1 Invitations 0 Offline
* Excludes moderators and previous
winners (Include)