Q: Identify and briefly describe the three types of constraints that can affect how you schedule resources
A: Constraint Description As Late As Possible (ALAP) Schedules the task as late as it can occur in the schedule without delaying subsequent tasks. [ Do not enter a constraint date with this constraint. [ As Soon As Possible (ASAP) Schedules the task to begin as early as it can occur. This is the default constraint for tasks. Do not enter a constraint date with this constraint. Finish No Earlier
Than (FNET) Schedules the task to finish on or after the constraint date. Use it to ensure that a task does not finish before a certain date. Finish No Later Than (FNLT) Schedules the task to finish on or before the constraint date. Use it to ensure that a task does not finish after a certain date. Must Finish On (MFO) Schedules the task to finish on the constraint date. Sets the early, scheduled, and late finish dates to the date that you type and anchors the task in the schedule. Must Start On (MSO) Schedules the task to start on the constraint date. Sets the early, scheduled, and late start dates to the date that you type and anchors the task in the schedule. Start No Earlier Than (SNET) Schedules the task to start on or after the constraint date. Use it to ensure that a task does not start before a specified date. Start No Later Than (SNLT) Schedules the task to start on or before the constraint date. Use it to ensure that a task does not start after a specified date. ]
Get an answer
Original conversation
User: Identify and briefly describe the three types of constraints that can affect how you schedule resources

Weegy: Constraint Description As Late As Possible (ALAP) Schedules the task as late as it can occur in the schedule without delaying subsequent tasks. [ Do not enter a constraint date with this constraint. [ As Soon As Possible (ASAP) Schedules the task to begin as early as it can occur. This is the default constraint for tasks. Do not enter a constraint date with this constraint. Finish No Earlier Than (FNET) Schedules the task to finish on or after the constraint date. Use it to ensure that a task does not finish before a certain date. Finish No Later Than (FNLT) Schedules the task to finish on or before the constraint date. Use it to ensure that a task does not finish after a certain date. Must Finish On (MFO) Schedules the task to finish on the constraint date. Sets the early, scheduled, and late finish dates to the date that you type and anchors the task in the schedule. Must Start On (MSO) Schedules the task to start on the constraint date. Sets the early, scheduled, and late start dates to the date that you type and anchors the task in the schedule. Start No Earlier Than (SNET) Schedules the task to start on or after the constraint date. Use it to ensure that a task does not start before a specified date. Start No Later Than (SNLT) Schedules the task to start on or before the constraint date. Use it to ensure that a task does not start after a specified date. ]
Controler|Points 1651|

User: Identify and briefly describe the three types of constraints that can affect how you schedule resources

Weegy: Constraint Description As Late As Possible (ALAP) Schedules the task as late as it can occur in the schedule without delaying subsequent tasks. [ Do not enter a constraint date with this constraint. [ As Soon As Possible (ASAP) Schedules the task to begin as early as it can occur. This is the default constraint for tasks. Do not enter a constraint date with this constraint. Finish No Earlier Than (FNET) Schedules the task to finish on or after the constraint date. Use it to ensure that a task does not finish before a certain date. Finish No Later Than (FNLT) Schedules the task to finish on or before the constraint date. Use it to ensure that a task does not finish after a certain date. Must Finish On (MFO) Schedules the task to finish on the constraint date. Sets the early, scheduled, and late finish dates to the date that you type and anchors the task in the schedule. Must Start On (MSO) Schedules the task to start on the constraint date. Sets the early, scheduled, and late start dates to the date that you type and anchors the task in the schedule. Start No Earlier Than (SNET) Schedules the task to start on or after the constraint date. Use it to ensure that a task does not start before a specified date. Start No Later Than (SNLT) Schedules the task to start on or before the constraint date. Use it to ensure that a task does not start after a specified date. ]
Controler|Points 1651|

Question
Asked 5/22/2012 5:04:19 PM
0 Answers/Comments
New answers
Rating

There are no new answers.

Comments

There are no comments.

Add an answer or comment
Log in or sign up first.
26,437,515 questions answered
Popular Conversations
What is the solution to the proportion? n/18 = 5/9 A. n = 2.5 B. n ...
Weegy: n/18 = 5/9; 9n = 5 * 18 9n = 90 n = 90/9 n = 10
10/12/2017 10:59:55 AM| 8 Answers
Which of the following has kinetic energy? a. a rock poised for a ...
Weegy: A bow that is drawn back by an archer. B. Has kinetic energy.
10/10/2017 2:00:05 PM| 3 Answers
What does everyone have planned for today " What type of sentence is ...
Weegy: "I think it would be best to study the problem carefully." The purpose of the above sentence is: It makes a ...
10/8/2017 2:18:49 PM| 2 Answers
What type of sentence tends to express a strong emotion? A. ...
Weegy: Do your work! The sentence is imperative. User: Which of the following pairs of words are homophones? ...
10/8/2017 2:25:51 PM| 2 Answers
_______ are words that are spelled alike, but have different ...
Weegy: "Near the computer" is a prepositional phrase. User: In which sentence is a homophone used correctly? ...
10/8/2017 2:29:20 PM| 2 Answers
In which one of the following sentences is a word misspelled? ...
Weegy: The sentence with a spelling mistake is: User: Which of the following is an example of an imperative sentence? ...
10/9/2017 8:45:54 AM| 2 Answers
Which of the following about the double-exposition concerto form is ...
Weegy: The development avoids the tonic is TRUE about the double-exposition concerto form. User: The first section ...
10/9/2017 11:33:19 AM| 2 Answers
Weegy Stuff
S
P
P
L
P
P
P
Points 135 [Total 2027] Ratings 11 Comments 25 Invitations 0 Offline
S
P
L
Points 97 [Total 119] Ratings 0 Comments 97 Invitations 0 Offline
S
Points 52 [Total 52] Ratings 4 Comments 12 Invitations 0 Offline
S
Points 3 [Total 3] Ratings 0 Comments 3 Invitations 0 Offline
S
Points 2 [Total 2] Ratings 0 Comments 2 Invitations 0 Offline
S
Points 2 [Total 2] Ratings 0 Comments 2 Invitations 0 Offline
S
Points 2 [Total 2] Ratings 0 Comments 2 Invitations 0 Offline
S
Points 1 [Total 1] Ratings 0 Comments 1 Invitations 0 Offline
S
Points 1 [Total 1] Ratings 0 Comments 1 Invitations 0 Offline
S
Points 1 [Total 1] Ratings 0 Comments 1 Invitations 0 Offline
* Excludes moderators and previous
winners (Include)
Home | Contact | Blog | About | Terms | Privacy | © Purple Inc.