Notice: Payments for answers will end 4/10/2017. Click for more info.
You have new items in your feed. Click to view.
Question and answer
Q: What are the three base calendars included in MS Project and what are the default values of each?
A: Project has three default base calendars ? Standard (traditional), 24 Hours, and .... Any task can be identified as a milestone by making the duration value 0.
Get an answer
Original conversation
User: What are the three base calendars included in MS Project and what are the default values of each?

Weegy: Project has three default base calendars ? Standard (traditional), 24 Hours, and .... Any task can be identified as a milestone by making the duration value 0.
concreterose|Points 560|

User: What is the difference between a base calendar and a resource calendar?





Weegy: The "Base Calendar" is the default calendar that is used for your planning. Any company holidays can be marked in this calendar as it would be applicable to the whole team. "Resource Calendar" is the calendar associated to a particular resource. [ If a particular resource is taking leave, you can mark those dates as non-working time.. by doing this, the tasks associated to the resource will move accordingly. ]
Expert answered|debnjerry|Points 26175|

Question
Asked 1/29/2012 5:11:15 PM
0 Answers/Comments
New answers
Rating

There are no new answers.

Comments

There are no comments.

Add an answer or comment
Log in or sign up first.
Questions asked by the same visitor
What is the difference between a base calendar and a resource calendar?
Question
Not Answered
Updated 2/6/2014 11:15:59 PM
1 Answer/Comment
Base calendars are templates that project calendars, task calendars, and resource calendars are derived from. They define the standard working and nonworking times for the enterprise.
A resource calendar, on the other hand, defines working and nonworking days and times for a specific resource or group of resources.

Added 2/6/2014 11:15:59 PM
This answer has been confirmed as correct and helpful.
26,640,842 questions answered
Popular Conversations
Suppose the U.S. can produce cars for a lower opportunity cost than ...
Weegy: Suppose the U.S. can produce cars for a lower opportunity cost than Japan while Japan has a comparative ...
2/13/2018 7:30:37 PM| 4 Answers
What's the simplified form of 2x + 3 x + 5? A. x 8 B. ...
Weegy: (2x^2)(3x^2) = 6x4 User: Simplify this expression: 13 + (–12) – (–5) = ? A. –6 B. 6 C. –30 ...
2/12/2018 11:53:02 PM| 3 Answers
Solve this equation: 80 = 3y + 2y + 4 + 1. A. y = 1/5 B. ...
Weegy: 80 = 3y + 2y + 4 + 1 80 = 5y + 5 80 - 5 = 5y -5y = -75 y = 15 User: Solve the inequality: 12p + 7 > 139 ...
2/14/2018 2:20:46 PM| 3 Answers
Solve the equation: 12y = 132. A. y = 11 B. y = 144 ...
Weegy: 12y = 132 User: Solve this equation: 2s + s + 12 = 132. A. s = 40 B. s = –30 C. s = 9 D. ...
2/14/2018 2:32:47 PM| 3 Answers
Weegy Stuff
S
L
Points 344 [Total 347] Ratings 10 Comments 214 Invitations 3 Offline
S
Points 89 [Total 89] Ratings 0 Comments 19 Invitations 7 Offline
S
P
L
P
P
Points 51 [Total 244] Ratings 0 Comments 51 Invitations 0 Offline
S
P
Points 41 [Total 85] Ratings 1 Comments 31 Invitations 0 Offline
S
1
L
L
P
R
P
L
P
P
R
Points 35 [Total 12646] Ratings 0 Comments 35 Invitations 0 Offline
S
Points 20 [Total 20] Ratings 2 Comments 0 Invitations 0 Online
S
P
Points 13 [Total 30] Ratings 0 Comments 13 Invitations 0 Offline
S
Points 11 [Total 11] Ratings 1 Comments 1 Invitations 0 Offline
S
Points 10 [Total 10] Ratings 0 Comments 0 Invitations 1 Offline
S
Points 10 [Total 11] Ratings 1 Comments 0 Invitations 0 Online
* Excludes moderators and previous
winners (Include)
Home | Contact | Blog | About | Terms | Privacy | © Purple Inc.