Question and answer
What are the three base calendars included in MS Project and what are the default values of each?
Project has three default base calendars ? Standard (traditional), 24 Hours, and .... Any task can be identified as a milestone by making the duration value 0.
Get an answer
Original conversation
User: What are the three base calendars included in MS Project and what are the default values of each?

Weegy: Project has three default base calendars ? Standard (traditional), 24 Hours, and .... Any task can be identified as a milestone by making the duration value 0.
concreterose|Points 560|

User: What is the difference between a base calendar and a resource calendar?





Weegy: The "Base Calendar" is the default calendar that is used for your planning. Any company holidays can be marked in this calendar as it would be applicable to the whole team. "Resource Calendar" is the calendar associated to a particular resource. [ If a particular resource is taking leave, you can mark those dates as non-working time.. by doing this, the tasks associated to the resource will move accordingly. ]
Expert answered|debnjerry|Points 26175|

Question
Asked 1/29/2012 5:11:15 PM
0 Answers/Comments
New answers
Rating

There are no new answers.

Comments

There are no comments.

Add an answer or comment
Log in or sign up first.
Questions asked by the same visitor
Given that an activity's normal time and cost are ten days and $400, and its crash time and cost are five days and $800, what is the activity's slope?
Weegy: Solved by delta cost over delta time, or 1. User: Identify and briefly describe the three types of constraints that can affect how you schedule resources. Weegy: ?A unique constraint (also referred to as a unique key constraint) is a rule that forbids duplicate values in one or more columns within a table. Unique and primary keys are the supported unique constraints. [ For example, a unique constraint can be defined on the supplier identifier in the supplier table to ensure that the same supplier identifier is not given to two suppliers. ?A primary key constraint is a column or combination of columns that has the same properties as a unique constraint. You can use a primary key and foreign key constraints to define relationships between tables. ?A foreign key constraint (also referred to as a referential constraint or a referential integrity constraint) is a logical rule about values in one or more columns in one or more tables. For example, a set of tables shares information about a corporation's suppliers. Occasionally, a supplier's name changes. You can define a referential constraint stating that the ID of the supplier in a table must match a supplier ID in the supplier information. This constraint prevents insert, update, or delete operations that would otherwise result in missing supplier information. ] User: What are the four types of resource constraints? Please list them and provide an example of each. Weegy: ?A unique constraint (also referred to as a unique key constraint) is a rule that forbids duplicate values in one or more columns within a table. Unique and primary keys are the supported unique constraints. [ [ For example, a unique constraint can be defined on the supplier identifier in the supplier table to ensure that the same supplier identifier is not given to two suppliers. ?A primary key constraint is a column or combination of columns that has the same properties as a unique constraint. You can use a primary key and ... (More)
Question
Expert Answered
Asked 1/29/2012 11:14:55 AM
0 Answers/Comments
What are the three base calendars included in MS Project and what are the default values of each?
Weegy: Project has three default base calendars – Standard (traditional), 24 Hours, and .... Any task can be identified as a milestone by making the duration value 0. (More)
Question
Expert Answered
Asked 1/29/2012 4:59:56 PM
0 Answers/Comments
What is the difference between a base calendar and a resource calendar?
Question
Not Answered
Updated 2/6/2014 11:15:59 PM
1 Answer/Comment
Base calendars are templates that project calendars, task calendars, and resource calendars are derived from. They define the standard working and nonworking times for the enterprise.
A resource calendar, on the other hand, defines working and nonworking days and times for a specific resource or group of resources.

Added 2/6/2014 11:15:59 PM
This answer has been confirmed as correct, not copied, and helpful.
20,743,780 questions answered
Popular Conversations
What is the slope of a line that runs parallel to y = x + 14? a0
Weegy: The slope of the graph of y = x is 1. User: What is the value of x if a rectangle has a perimeter of 50, a ...
5/5/2015 9:42:50 AM| 4 Answers
Which of the following equations will make a V-shaped graph? y = ...
Weegy: Please use the link below to see a graph of function y=4(3)^x User: All of the following points lie on the ...
5/5/2015 9:48:20 AM| 4 Answers
Find the product mentally. (r - s)^2
Weegy: (r - s)^2 =r^2 - rs - rs + s^2 =r^2 - 2rs + s^2 User: Find the product mentally. (2m - 9)^2 User: Find ...
5/5/2015 10:38:21 AM| 3 Answers
Identify the compound sentence. A. The rain began to ...
Weegy: "The rain began to fall, but we did not want to leave" is the compound sentence.
5/5/2015 4:02:30 PM| 3 Answers
Read the sentences. Queen Elizabeth rode in a carriage. The ...
Weegy: The sentence that best uses subordinate participial phrase is: Queen Elizabeth, drawn by two Windsor Greys, rode ...
5/5/2015 4:44:53 PM| 3 Answers
What event prompted the Protestant Reformation? A. Martin Luther ...
Weegy: A. Martin Luther posted his Ninety-Five Theses on a church door. User: Find the equation of the circle with ...
5/5/2015 5:27:18 PM| 3 Answers
Which is a balanced equation for this reaction? A. C2H6 + O2? H2O + ...
Weegy: A balanced equation among these reactions is 2C2H6 + 5O2 3H2O + 4CO2. User: Balance the equation by ...
5/5/2015 8:16:48 AM| 2 Answers
Find the distance between the points (-4, -5) and (3, -1).
Weegy: The distance between the points (-4 , -5) and (-1 , -1) is 5. User: Solve x 2 - 8x + 3 = 0 by completing the ...
5/5/2015 8:19:44 AM| 2 Answers
Which choice is the equation of a line that passes through the point ...
Weegy: Simplifying 5x + -4y = 12 Solving 5x + -4y = 12 Solving for variable 'x'. Move all terms containing x to the ...
5/5/2015 8:37:33 AM| 2 Answers
Weegy Stuff
S
Points 245 [Total 775]| Ratings 0| Comments 245| Invitations 0|Offline
S
1
Points 107 [Total 499]| Ratings 1| Comments 97| Invitations 0|Online
S
P
C
L
P
L
1
P
P
1
P
1
Points 67 [Total 8813]| Ratings 0| Comments 67| Invitations 0|Offline
S
1
L
L
Points 44 [Total 8227]| Ratings 0| Comments 44| Invitations 0|Offline
S
Points 37 [Total 45]| Ratings 0| Comments 37| Invitations 0|Offline
S
Points 24 [Total 24]| Ratings 1| Comments 14| Invitations 0|Offline
S
L
Points 15 [Total 3769]| Ratings 0| Comments 15| Invitations 0|Offline
S
Points 10 [Total 179]| Ratings 1| Comments 0| Invitations 0|Online
S
Points 7 [Total 27]| Ratings 0| Comments 7| Invitations 0|Offline
S
Points 3 [Total 3]| Ratings 0| Comments 3| Invitations 0|Online
Home | Contact | Blog | About | Terms | Privacy | Social | ©2015 Purple Inc.